Phase 1
Painters are applying the 2nd coat of paint below the chair rail on the 3rd floor. Carpet is being installed on the 2nd floor and removal of carpet on the 1st floor should be completed by the end of today.
Phase 2
The painters are applying the 2nd coat of paint above the chair rail on the 2nd floor. Carpet is being installed on the 3rd floor with removal of carpet expected on the 2nd floor to begin on Thursday.
Greg - Operations