Friday, January 14, 2011

Update as of January 14, 2011

In Phase 1 carpet installation will be finished on the 3rd floor today, except for the areas in front of the elevator and the fire doors. These areas will be completed on Monday. Removal of old carpet on the 2nd floor has also begun today.

The portion of the walls below the chair rail on the first floor are receiving the first coat of paint today in Phase 1.

In Phase 2 the painters will begin installing the chair rail on the first floor, starting on Monday. As well, carpet removal will begin on Monday on the 3rd floor, with installation of the new carpet on Tuesday or Wednesday.


Greg - Operations

No comments:

Post a Comment