Chair rail installation continues in Phase 2 with expected completion of installation on Tuesday or Wednesday. The stairwells have received one coat of paint. Carpet removal and installation has begun on the 3rd floor. On the 2nd floor the walls are getting a 2nd coat of paint above the chair rail, as well as one coat on the chair rail and one coat below the chair rail.
In Phase 1 on the 1st floor the painters are putting on the 1st coat below the chair rail. After which they will move to the 3rd floor to paint the 2nd coat on the door frames and below the chair rail, as well as the first coat of paint on the baseboard.
Carpet removal is in progress on the 2nd floor on Phase 1 and installation is to follow.