Monday, January 10, 2011

Progress as of January 10

The ceilings have been sprayed two coats. There have been deficiencies noted and they will be dealt with this week.

We are installing chair rail on Phase 2 on the third floor, as well as painting the upper half of the wall as of today.

The painting of the chair rail throughout in Phase 1 will be complete today. We will start painting above the chair rail today.

If everything goes as predicted, carpet will be removed from the third floor on Phase 1 on Thursday or Friday. I will let you know once it is confirmed.

Greg- Operations