The painting crews in both building are currently working on the first floor and are expecting to complete the floor early tomorrow. They will then be moving on to painting the stairwells and amenity rooms over the next couple of days.
Greg
Wolfgang
Thursday, January 27, 2011
Monday, January 24, 2011
Work progress as of January 24, 2011
We are projecting to be completed painting by February 5th. We will completing a deficiency walk through with the strata council at that time.
Phase 1
The second coat of paint below the chair rail has been applied to the walls and now the painters are focussed on the baseboards. We will be working on stairwells and amenity room this week. Carpet has been installed on all three floors.
Phase 2
Chair rail is now completely installed and painted on all three floors. The third floor should be finished with painting by tomorrow, January 25th. Carpet has been installed on all three floors.
Greg
Operations
Phase 1
The second coat of paint below the chair rail has been applied to the walls and now the painters are focussed on the baseboards. We will be working on stairwells and amenity room this week. Carpet has been installed on all three floors.
Phase 2
Chair rail is now completely installed and painted on all three floors. The third floor should be finished with painting by tomorrow, January 25th. Carpet has been installed on all three floors.
Greg
Operations
Friday, January 21, 2011
Progress update as of January 21st
Phase 1
Painters are working on the 3rd floor applying the final coats of paint to the chair rail and the wall below the chair rail. They are also working painting the baseboard on the 3rd floor.
Phase 2
The painters in phase 2 are also working on the 3rd floor applying the final coats of paint to the chair rail and the wall below the chair rail. As well as painting the baseboard.
Greg
Wolfgang Painters
Painters are working on the 3rd floor applying the final coats of paint to the chair rail and the wall below the chair rail. They are also working painting the baseboard on the 3rd floor.
Phase 2
The painters in phase 2 are also working on the 3rd floor applying the final coats of paint to the chair rail and the wall below the chair rail. As well as painting the baseboard.
Greg
Wolfgang Painters
Tuesday, January 18, 2011
Work progress as of January 18, 2011
Phase 1
Painters are applying the 2nd coat of paint below the chair rail on the 3rd floor. Carpet is being installed on the 2nd floor and removal of carpet on the 1st floor should be completed by the end of today.
Phase 2
The painters are applying the 2nd coat of paint above the chair rail on the 2nd floor. Carpet is being installed on the 3rd floor with removal of carpet expected on the 2nd floor to begin on Thursday.
Greg - Operations
Painters are applying the 2nd coat of paint below the chair rail on the 3rd floor. Carpet is being installed on the 2nd floor and removal of carpet on the 1st floor should be completed by the end of today.
Phase 2
The painters are applying the 2nd coat of paint above the chair rail on the 2nd floor. Carpet is being installed on the 3rd floor with removal of carpet expected on the 2nd floor to begin on Thursday.
Greg - Operations
Monday, January 17, 2011
Progress update as of January 17th
Chair rail installation continues in Phase 2 with expected completion of installation on Tuesday or Wednesday. The stairwells have received one coat of paint. Carpet removal and installation has begun on the 3rd floor. On the 2nd floor the walls are getting a 2nd coat of paint above the chair rail, as well as one coat on the chair rail and one coat below the chair rail.
In Phase 1 on the 1st floor the painters are putting on the 1st coat below the chair rail. After which they will move to the 3rd floor to paint the 2nd coat on the door frames and below the chair rail, as well as the first coat of paint on the baseboard.
Carpet removal is in progress on the 2nd floor on Phase 1 and installation is to follow.
In Phase 1 on the 1st floor the painters are putting on the 1st coat below the chair rail. After which they will move to the 3rd floor to paint the 2nd coat on the door frames and below the chair rail, as well as the first coat of paint on the baseboard.
Carpet removal is in progress on the 2nd floor on Phase 1 and installation is to follow.
Friday, January 14, 2011
Update as of January 14, 2011
In Phase 1 carpet installation will be finished on the 3rd floor today, except for the areas in front of the elevator and the fire doors. These areas will be completed on Monday. Removal of old carpet on the 2nd floor has also begun today.
The portion of the walls below the chair rail on the first floor are receiving the first coat of paint today in Phase 1.
In Phase 2 the painters will begin installing the chair rail on the first floor, starting on Monday. As well, carpet removal will begin on Monday on the 3rd floor, with installation of the new carpet on Tuesday or Wednesday.
Greg - Operations
The portion of the walls below the chair rail on the first floor are receiving the first coat of paint today in Phase 1.
In Phase 2 the painters will begin installing the chair rail on the first floor, starting on Monday. As well, carpet removal will begin on Monday on the 3rd floor, with installation of the new carpet on Tuesday or Wednesday.
Greg - Operations
Wednesday, January 12, 2011
Update January 12
The removal of carpet will start tomorrow(Thursday) on the third floor in the North (Phase2) building.
The chair rail has been installed on the third floor of phase 1 and we have moved on to the installation on the second floor.
Greg - Operations
The chair rail has been installed on the third floor of phase 1 and we have moved on to the installation on the second floor.
Greg - Operations