Friday, December 31, 2010

It is about to start!

It will be a great way to start your New Year with an updated paint and flooring job. The painting and wallpaper removal will start on Monday. The noise from the project should not be too bad. The worst sounds will be the paint sprayers, the chop shaw for cutting the chair rail, and the compressor for nailing the chair rail. We will be working during the day time, so hopefully it is not too much of a disruption. We will do our best to keep everything neat in tidy. We will try to clean as we go, but we will be doing a much more thorough cleaning job at the end of each day. This is minor construction so please bare with us. 

Happy New Year,
Greg - Operations - Wolfgang

Thursday, December 23, 2010

Happy Holidays

Wolfgang Commercial Painters and Mira Floors is wishing everyone a happy and safe holiday!

The Wolfgang Team and Mira Floors

Wednesday, December 22, 2010

Timeline, Hours, and Work Flow

Timeline of Project
Phase 1
- Wolfgang Painters
-removal of wallpaper, painting of ceilings, chair rail, and wall above chair rail, and amenity rooms and first coat on suite frames
- duration 4 weeks
-Monday January 3 to Friday January 28
Phase 2
- Mira Floors
-removal of carpet and reinstall of carpet tile in hallways
-removal and installation in stairwells will be left till last
-duration 4 weeks
- Monday January 17 to Friday February 11(dependent on carpet delivery)
Phase 3
- Wolfgang Painters
-painting of walls below chair rail and baseboards and final coat on suite frames and painting of stairwells
- duration - follows the carpet installation
-the final carpet installation is scheduled for February 11 - the painting will be
completed by February 18

Hours of Work
-8am to 6pm
-Monday to Friday
- this does not mean we will be there during all of these hours but it does mean we will not be outside those hours

Work Flow
- Work will commence in both buildings on the third floor and work down to the main floor leaving the stairwells to the end
- painting will be occurring in both buildings simultaneously


Wednesday, December 15, 2010

Thanks and Products

Thanks for signing up for information about your job. We currently have 11 subscribers. Please let other people in the strata know about the job blog.

We will be using water based acrylics from ICI for this job. We will be using Lifemaster Eggshell on the walls. This is a zero VOC acrylic, with a slight musty smell. We will be using Diamond Semi-Gloss on all the trim. This is a very durable acrylic with a slightly stronger smell.

Greg - Wolfgang Operations

Thursday, December 9, 2010

Update

It will all start on January 3, 2011. We will be painting both buildings at once. Jason Chapman will be in charge of the team on one building and Tej Kahlon will be in charge of the team on the second building. These guys are excellent at their job, and I can ensure you an excellent finished product.

Greg - Operations

Tuesday, November 30, 2010

Excited to start!

Wolfgang Commercial Painters is getting excited about beginning your painting project. Please stay tuned for the details to come. Greg in Operations