Timeline of Project
Phase 1 - Wolfgang Painters
-removal of wallpaper, painting of ceilings, chair rail, and wall above chair rail, and amenity rooms and first coat on suite frames
- duration 4 weeks
-Monday January 3 to Friday January 28
Phase 2
- Mira Floors
-removal of carpet and reinstall of carpet tile in hallways
-removal and installation in stairwells will be left till last
-duration 4 weeks
- Monday January 17 to Friday February 11(dependent on carpet delivery)
Phase 3
- Wolfgang Painters
-painting of walls below chair rail and baseboards and final coat on suite frames and painting of stairwells
- duration - follows the carpet installation
-the final carpet installation is scheduled for February 11 - the painting will be
completed by February 18
Hours of Work
-8am to 6pm
-Monday to Friday
- this does not mean we will be there during all of these hours but it does mean we will not be outside those hours
Work Flow
- Work will commence in both buildings on the third floor and work down to the main floor leaving the stairwells to the end
- painting will be occurring in both buildings simultaneously
Nice blog! Thanks for the update, keep up the good work!
ReplyDeleteThanks Erin! Greg
ReplyDelete